As part of the TTC’s continuing modernization efforts the turnstiles at the main entrance and the high gates at the automatic entrances to Sheppard-Yonge Station will be replaced with new paddle-style fare gates.

Construction at the main entrance is scheduled to start on December 8.

  • The construction will be done in two phases. Customers will enter the station through the collector booth aisle or through a temporary station collector entrance
  • A PRESTO card reader will be available for PRESTO card customers during both phases of construction.

Construction at the Hullmark entrance is scheduled to start on December 10.

  • The construction will be done in two phases.
    • Phase one Customers will enter and exit the station through the collector booth aisle.
    • Phase two Customers will enter and exit the station through a crash gate collector aisle. The collector booth will be closed for sales.
  • A PRESTO card reader will be available during construction
  • When construction ends customers will only be able to access this entrance with a TTC Pass or PRESTO card. 

Construction at the Sheppard West automatic entrance is scheduled to start on December 11.

  • The entrance will be closed from 11 p.m. December 11 until 6 a.m. December 14.
  • When the entrance re-opens on December 14 customers will enter the station through a temporary station collector.
  • When construction ends, customers will only be able to access this entrance by PRESTO card.

Construction at the Harlandale automatic entrance is scheduled to start on December 14.

  • The entrance will be closed from 11 p.m. December 14 until 6 a.m. December 16.
  • When the entrance re-opens on December 17 customers will enter the station through a temporary station collector aisle.
  • When construction ends customers will only be able to access this entrance with a PRESTO card.

Construction at the Poyntz automatic entrance is scheduled to start in mid-March 2018.. The entrance will close in mid-February for some pre-construction work that is needed before the fare gate construction begins

  • When construction ends customers will only be able to access this entrance by PRESTO card.

To purchase a PRESTO card visit the Gateway Newstand in Sheppard-Yonge Station or visit prestocard.ca.

To learn more about PRESTO visit ttc.ca/presto.